Water Site Upgrade Scheme

The project sSope

As part of a £49.3M upgrade scheme, our client required a security improvement for their reservoir site. The scope was to manufacture and install various security rated products to safeguard the buildings from further threat and to enhance security to minimise the risk of future incidents.

The solution

Some of the access cover requirements involved ground clearing to take place, and new concrete slabs to be put in place. Given the urgency of the project. A Steelway surveyor was dispatched immediately to allow identification of the detailed scope of supply and installation.

Steelway's project management team worked closely with the client to produce all necessary documents, including full detailed drawings, quotation, a detailed programme of works and full RAMS for installation. A site survey was conducted by Steelway prior to installation to collect full information and to ensure seamless execution of the project.  

Within 10 days a survey, quotation, and full drawings had been created and released of or approval. Within 4-5 weeks full installation was taking place and was completed within the agreed timescale.

The placement of some of the access covers posed difficulties for maintenance tasks, specifically the preparation,  removal and re installation of newcovers, requiring extra effort to coordinate access and fitting, This aspect of the work was also accommodated by the Steelway project and installation teams.

Steelway provided a unique solution tailored to the specific needs of the site. The design ensured that all products could be safely transported and lifted into place using approved equipment, allowing for a safe, efficient, secure and on time installation.

Products that were supplied and installed

  • Security rated doors (SR2)
  • Window Bar sets (SR3)
  • Anti climb (collar and roof protection)
  • SR4 rated Upstand & Flushfitting access covers

 

No items found.
Copyright Steelway Fensecure Ltd 2023. All Rights Reserved. Steelway is part of the Northern Industries Family
Website by Gravitas

Water Site Upgrade Scheme

The project sSope

As part of a £49.3M upgrade scheme, our client required a security improvement for their reservoir site. The scope was to manufacture and install various security rated products to safeguard the buildings from further threat and to enhance security to minimise the risk of future incidents.

The solution

Some of the access cover requirements involved ground clearing to take place, and new concrete slabs to be put in place. Given the urgency of the project. A Steelway surveyor was dispatched immediately to allow identification of the detailed scope of supply and installation.

Steelway's project management team worked closely with the client to produce all necessary documents, including full detailed drawings, quotation, a detailed programme of works and full RAMS for installation. A site survey was conducted by Steelway prior to installation to collect full information and to ensure seamless execution of the project.  

Within 10 days a survey, quotation, and full drawings had been created and released of or approval. Within 4-5 weeks full installation was taking place and was completed within the agreed timescale.

The placement of some of the access covers posed difficulties for maintenance tasks, specifically the preparation,  removal and re installation of newcovers, requiring extra effort to coordinate access and fitting, This aspect of the work was also accommodated by the Steelway project and installation teams.

Steelway provided a unique solution tailored to the specific needs of the site. The design ensured that all products could be safely transported and lifted into place using approved equipment, allowing for a safe, efficient, secure and on time installation.

Products that were supplied and installed

  • Security rated doors (SR2)
  • Window Bar sets (SR3)
  • Anti climb (collar and roof protection)
  • SR4 rated Upstand & Flushfitting access covers

 

No items found.
Copyright Steelway Fensecure Ltd 2023. All Rights Reserved. Steelway is part of the Northern Industries Family
Website by Gravitas

Water Site Upgrade Scheme

The project sSope

As part of a £49.3M upgrade scheme, our client required a security improvement for their reservoir site. The scope was to manufacture and install various security rated products to safeguard the buildings from further threat and to enhance security to minimise the risk of future incidents.

The solution

Some of the access cover requirements involved ground clearing to take place, and new concrete slabs to be put in place. Given the urgency of the project. A Steelway surveyor was dispatched immediately to allow identification of the detailed scope of supply and installation.

Steelway's project management team worked closely with the client to produce all necessary documents, including full detailed drawings, quotation, a detailed programme of works and full RAMS for installation. A site survey was conducted by Steelway prior to installation to collect full information and to ensure seamless execution of the project.  

Within 10 days a survey, quotation, and full drawings had been created and released of or approval. Within 4-5 weeks full installation was taking place and was completed within the agreed timescale.

The placement of some of the access covers posed difficulties for maintenance tasks, specifically the preparation,  removal and re installation of newcovers, requiring extra effort to coordinate access and fitting, This aspect of the work was also accommodated by the Steelway project and installation teams.

Steelway provided a unique solution tailored to the specific needs of the site. The design ensured that all products could be safely transported and lifted into place using approved equipment, allowing for a safe, efficient, secure and on time installation.

Products that were supplied and installed

  • Security rated doors (SR2)
  • Window Bar sets (SR3)
  • Anti climb (collar and roof protection)
  • SR4 rated Upstand & Flushfitting access covers

 

No items found.
Copyright Steelway Fensecure Ltd 2023. All Rights Reserved. Steelway is part of the Northern Industries Family
Website by Gravitas

Water Site Upgrade Scheme

The project sSope

As part of a £49.3M upgrade scheme, our client required a security improvement for their reservoir site. The scope was to manufacture and install various security rated products to safeguard the buildings from further threat and to enhance security to minimise the risk of future incidents.

The solution

Some of the access cover requirements involved ground clearing to take place, and new concrete slabs to be put in place. Given the urgency of the project. A Steelway surveyor was dispatched immediately to allow identification of the detailed scope of supply and installation.

Steelway's project management team worked closely with the client to produce all necessary documents, including full detailed drawings, quotation, a detailed programme of works and full RAMS for installation. A site survey was conducted by Steelway prior to installation to collect full information and to ensure seamless execution of the project.  

Within 10 days a survey, quotation, and full drawings had been created and released of or approval. Within 4-5 weeks full installation was taking place and was completed within the agreed timescale.

The placement of some of the access covers posed difficulties for maintenance tasks, specifically the preparation,  removal and re installation of newcovers, requiring extra effort to coordinate access and fitting, This aspect of the work was also accommodated by the Steelway project and installation teams.

Steelway provided a unique solution tailored to the specific needs of the site. The design ensured that all products could be safely transported and lifted into place using approved equipment, allowing for a safe, efficient, secure and on time installation.

Products that were supplied and installed

  • Security rated doors (SR2)
  • Window Bar sets (SR3)
  • Anti climb (collar and roof protection)
  • SR4 rated Upstand & Flushfitting access covers

 

No items found.
Copyright Steelway Fensecure Ltd 2023. All Rights Reserved. Steelway is part of the Northern Industries Family
Website by Gravitas

Water Site Upgrade Scheme

The project sSope

As part of a £49.3M upgrade scheme, our client required a security improvement for their reservoir site. The scope was to manufacture and install various security rated products to safeguard the buildings from further threat and to enhance security to minimise the risk of future incidents.

The solution

Some of the access cover requirements involved ground clearing to take place, and new concrete slabs to be put in place. Given the urgency of the project. A Steelway surveyor was dispatched immediately to allow identification of the detailed scope of supply and installation.

Steelway's project management team worked closely with the client to produce all necessary documents, including full detailed drawings, quotation, a detailed programme of works and full RAMS for installation. A site survey was conducted by Steelway prior to installation to collect full information and to ensure seamless execution of the project.  

Within 10 days a survey, quotation, and full drawings had been created and released of or approval. Within 4-5 weeks full installation was taking place and was completed within the agreed timescale.

The placement of some of the access covers posed difficulties for maintenance tasks, specifically the preparation,  removal and re installation of newcovers, requiring extra effort to coordinate access and fitting, This aspect of the work was also accommodated by the Steelway project and installation teams.

Steelway provided a unique solution tailored to the specific needs of the site. The design ensured that all products could be safely transported and lifted into place using approved equipment, allowing for a safe, efficient, secure and on time installation.

Products that were supplied and installed

  • Security rated doors (SR2)
  • Window Bar sets (SR3)
  • Anti climb (collar and roof protection)
  • SR4 rated Upstand & Flushfitting access covers

 

No items found.

CEL Sheet Metal Ltd is a UK based sheet metal and assembly business, offering a variety of services that can effectively replace your existing sub-contract manufacturing requirements.

+44 (0) 1952 200 741
sales@celsheetmetal.com
Stafford Park 11
Telford
Shropshire
TF3 3AY
Copyright CEL Sheetmetal ltd 2023. All Rights Reserved.   Privacy Policy   |    Terms of Service    |    Website by Gravitas